How bathroom pods are installed: from factory to finished room

Installing a bathroom pod takes far less time on site than building a bathroom, but it relies on good planning beforehand. These are the steps from the first drawing to a room that is ready to use.

Cubo Module bathroom pod in the factory, ready for delivery, with the frame and plumbing visible

1. Design stage: fix the interfaces

Before anything is made, the pod has to fit the building and the building has to fit the pod. The architect and engineers agree on the pod dimensions, the wall and ceiling build-up around it, the position of every connection (water, waste, power, ventilation) and how the pod is supported. For a step-free entrance, the structural slab usually gets a recess so the pod floor finishes level with the floor outside.

2. Mock-up and approval

For a series, the first pod is built as a mock-up. The client inspects it in the factory or by video, signs it off and the mock-up becomes the quality reference for every unit that follows.

3. Production and testing

Pods are produced while the building shell goes up on site. Each unit is pressure-tested, the electrical installation is checked, and the pod is cleaned, protected and labelled with its final position in the building.

4. Delivery and lifting

Pods are delivered in the order they will be installed, ideally straight from the truck to the floor. They are lifted by crane into an open section of the façade or onto a landing platform, then moved into position on rollers or skates. Where a crane cannot reach, pods can be brought in through larger openings and moved inside the building. Planning the route for every floor before delivery avoids storing units on site.

5. Placing and levelling

Each pod is placed on its marked position, levelled on adjustable feet or shims and fixed to the structure. A level, square pod is important for the joints to the surrounding walls and for doors to close properly.

6. Connection

The installer connects cold water, hot water, waste, power and ventilation at the prepared points. Because the pipework inside the pod was tested in the factory, the on-site test is limited to the new connections. Service access panels let the installer reach the connections without opening tiled walls.

7. Finishing to the building

Finally, the joints between the pod and the building are closed: wall linings around the pod, the door frame, the ceiling junction and the floor threshold. The protective film comes off at the very end, when the surrounding trades are finished.

How long does it take?

On site, placing and connecting one pod takes [X] for our standard units, depending on access and the number of pods per day. The total programme saving comes from building the bathrooms in parallel with the shell, not only from fast installation.

Standalone pods

A standalone bathroom, for example in a garden building or at a campsite, is installed on simple strip foundations or a level slab, connected to water, sewage and power, and finished with a gravel border. Our smoking rooms and fitness rooms are installed in the same way, as modules joined on site.

Frequently asked questions

Does a pod need a crane?

In new buildings, usually yes, because pods are lifted in before the façade is closed. In existing buildings or ground floors, pods can be moved in on skates through a large opening. Where neither is possible, a flat-pack kit is used.

Who connects the pod on site?

Either our own installation team or your contractor, using our connection drawings. The scope is agreed in the quote.

How is the pod protected until handover?

Pods leave the factory cleaned and protected with film and covers. The protection stays on until the surrounding work is finished.